What to expect in the first week

Explanation. The MES is now watching a real line beside the system already in charge there. Here is what it will get wrong, what that means, and what is worth comparing.

Nothing on this page is a promise. It is the list of things that have surprised people on the first day of a shadow run, written down so they surprise nobody again.

Day one: three things that look wrong and are correct

OEE says unknown, not a number. The MES refuses to compute a KPI from history it does not have. It was not subscribed before you started it, so the first window is short and mostly unknown. Numbers appear as observation accumulates — a shift, then a day, then a week. See Reading OEE.

The downtime pareto is close to 100 % unlabelled. Nothing on an OPC-fed line labels a stop. The MES names that bar unlabelled rather than filing it under "other", because a pareto that hides its own ignorance convinces a plant it has data it does not have. Reason codes are an operator workflow somebody adds later; they are not a missing feature you are waiting on.

A machine with no scrap counter shows no quality figure. Blank in the worksheet means unknown on the screen. Never zero.

Week one: the four mistakes that are actually yours to fix

These are the ones worth chasing, in the order they usually appear.

1. Tag-map mistakes

The commonest first-week finding is a tag that was mapped to the wrong meaning, not a tag that was unreadable — fsmes opc-verify catches unreadable on day one. What it cannot catch is a plausible wrong answer: the good counter pointed at the infeed rather than the outfeed, an analog that is the setpoint and not the measurement, a state tag that belongs to the neighbouring machine.

The symptom is a number that is steadily wrong in one direction. Fix it in the worksheet, regenerate the tag map, restart the agent. Never in code.

2. Planned stops mislabelled as downtime

If a changeover, a planned clean or a break maps to down, every availability figure after it is wrong, and the shape of the pareto sends people to the wrong machine. This is the single most damaging mapping mistake, and it is invisible unless somebody who knows the line looks at a day of state history and says "that stop was a changeover".

Do that once, in week one, with the person who runs the line. It is an hour, and it decides what every availability number you ever report means. The mapping table is in the Engineering guide.

3. Counter resets

Counters reset — at shift change, at power cycle, at order change, at a PLC download. The MES books production from counter increases and re-baselines on a reset rather than booking a negative or a huge jump, so a reset does not corrupt the count. What it does do is make performance read unknown for the window it happened in, which looks like a gap.

Ask Engineering when each counter resets and write it in the worksheet's notes column. It will not change the software's behaviour; it will change how quickly somebody recognises the gap.

4. The agent not running

The window the agent was not watching cannot be reconstructed afterwards. That is deliberate — see Never invent production — and it means an agent that died at 02:00 and was restarted at 08:00 leaves six hours that will read unknown forever.

Run it under a supervisor from the first day (deploy has the systemd unit), and check on the first morning that it is still the process you started.

What to compare against the system already in charge

Compare the things both systems measure the same way:

Worth comparing Why
Good count per order, per shift Both count the same physical parts. A steady difference is a tag-map error; a difference that appears only at order boundaries is a booking-rule difference, which is the interesting one.
The shape of the day — when the line ran and when it stopped Two systems watching the same tags should agree about when the machine was moving, even if they label the stops differently.
The longest stops Both will have them. Whether they agree on which machine stopped first is a real test of the tag map.

What is not worth comparing, yet

Not yet Why
OEE, as a single number Two systems almost never define availability over the same calendar. Until you have agreed what counts as planned time, comparing the number compares the definitions, not the plants.
The downtime pareto The incumbent has reason codes entered by people. This MES has none in week one. The comparison is between labelled and unlabelled, which tells you nothing about either system.
Anything in the first two hours Too short a window for any of the KPIs to leave unknown.
Scrap, unless every machine has a scrap counter An unknown compared against a number is not a comparison.

The honest summary to give whoever asked for this

After a week you can say, with evidence: whether the tag map is right, whether this MES sees the same line the incumbent sees, and how far apart the two counts are. You cannot yet say whether its OEE is better, because in week one it is mostly unknown and unknown is the correct answer.